On Monday March 24, 2008, the Commission voted to hire G. Robert George and Associates as the engineer for the Schooner Road project. Preliminary Project Design will take approximately 19 days, Design Services will take approximately 40 days, Permitting and Agency Coordination Services will take approximately 39 days, Bidding and Contractor Selection will take approximately 29 days, Construction will take approximately 120 days and project closeout will take approximately 14 days. The project is estimated to be complete in March of 2009. If you have any questions please email David Hoffman at hoffmand@jipsd.org.